Project Difficulties and Restrictions
The Cross Rail tunnel boring machine was to commence it's drive at Lords Hill Bridge, passing directly underneath it.
In order to prevent damage to the north bridge abutment by the tunnelling machine, the whole of the ground beneath the bridge had to be replaced with a weak concrete by constructing interlocking 1200mm diameter piles to 13.0m within a headroom constraint of 5.1m.