Project Difficulties and Restrictions
The project required the installation of 6No 900mm diameter piles which were installed underneath the railway, within the confines of a 3.5m high x 3.5m wide flood arch, and 20No 750mm diameter piles, to be installed at track level next to the operational line.
The site restrictions significantly limited the size of the piling equipment which could be used for the project.